Design and construction of 93,300 SF of administration and support space, 20,000 SF of transitional housing, and 139,100 SF of detention center.
Mechanical Highlights
500T chilled water system
5,000 MBH heating water system
173,000 CFM total
Radiant floor heating
Secure air flow devices and detention plumbing fixtures
Owner
San Mateo County Sheriff’s Office
General Contractor
Sundt Construction
Architect
HOK
Mechanical Engineer
Frank M. Booth, Inc.
Year Complete
2016
Size
252,400 SF 833 Beds
Contract Type
Design-Build
Certifications
LEED Silver
At A Glance
This project delivers 93,300 SF of administration and support space, 20,000 SF of transitional housing, and 139,100 SF of detention center. A high-efficiency 4-pipe central plant with radiant floor heating in the housing day rooms supports LEED Silver certification.